Factoria Blvd Stormwater Improvements Project Online Open House
Share Factoria Blvd Stormwater Improvements Project Online Open House on FacebookShare Factoria Blvd Stormwater Improvements Project Online Open House on TwitterShare Factoria Blvd Stormwater Improvements Project Online Open House on LinkedinEmail Factoria Blvd Stormwater Improvements Project Online Open House link
Thank you for your interest in this project. At this time, the Online Open House has concluded. If you have any additional questions or comments, please contact Birol Shaha, bshaha@bellevuewa.gov or 425-452-4477.
What is the project?
Bellevue Utilities is pursuing a project to improve the stormwater system along Factoria Blvd to reduce the risks of street flooding during heavy storm events.
Construction will be located along Factoria Blvd between SE 38th Street and SE 36th Street (see map at right). The project is currently in planning phase, with construction projected to start in Spring 2022.
Thank you for your interest in this project. At this time, the Online Open House has concluded. If you have any additional questions or comments, please contact Birol Shaha, bshaha@bellevuewa.gov or 425-452-4477.
What is the project?
Bellevue Utilities is pursuing a project to improve the stormwater system along Factoria Blvd to reduce the risks of street flooding during heavy storm events.
Construction will be located along Factoria Blvd between SE 38th Street and SE 36th Street (see map at right). The project is currently in planning phase, with construction projected to start in Spring 2022.
Factoria Blvd Stormwater Improvements Project Online Open House is currently at this stage
Development and analysis of potential project designs (alternatives analysis, and preliminary design)
Design - 2021
this is an upcoming stage for Factoria Blvd Stormwater Improvements Project Online Open House
Develop detailed design, permit acquisition, and agency coordination
Franchise utility relocation
Pre-Construction - Early 2022
this is an upcoming stage for Factoria Blvd Stormwater Improvements Project Online Open House
Solicit construction contractor and plan construction logistics
Begin Construction - Spring/Summer 2022
this is an upcoming stage for Factoria Blvd Stormwater Improvements Project Online Open House
Construction activities
Complete Construction - Summer 2023
this is an upcoming stage for Factoria Blvd Stormwater Improvements Project Online Open House
Complete restoration
Custom
The City of Bellevue assures that no person shall on the grounds of race, color, national origin, or sex as provided by Title VI of the Civil Rights Act of 1964, and related statutes, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any City of Bellevue program or activity. Any person who believes his/her Title VI protection has been violated may file a complaint with the ADA/Title VI Administrator. For Title VI complaint forms and advice, please contact the ADA/Title VI Administrator at 425-452-6168.
Custom
For alternate formats, interpreters, or reasonable accommodation requests please phone at least 48 hours in advance 425-452-5215 (voice) or jguthrie@bellevuewa.gov. For complaints regarding accommodations, contact City of Bellevue ADA/Title VI Administrator at 425-452-6168 (voice) or email ADATitleVI@bellevuewa.gov. If you are deaf or hard of hearing dial 711.